Predictability: Sprint completion
Purpose
Deliver most issues we've put into the sprint.
Expectation
Min. 80% sprint completion.
How an indicator is measured
Sprint completion % = sum of story points of issues put and resolved in the sprint divided by sum of story points of all issues put in the sprint
Action
If Sprint completion is low, it could signal:
- cycle time of issues is too high,
- grooming ceremony is not working properly, meaning we put too complex or uncertain issues in the sprint,
- there is a high number of ad-hoc tasks entering the sprint in an unplanned manner.