Escalating RFIs
SUMMARY
The GENERAL FOREMAN will open an RFI. The SUPERINTENDENT will either answer the RFI or Escalate the RFI.
PROCEDURE
- If the RFI can be answered internally, the Superintendent will answer it.
- Click Add Response
- Type in your Response
- Click Post Response.
- Click Return to RFI Manager’s Court.
- RFI Manager will close the RFI.
- If the RFI cannot be answered internally, the Superintendent will route the RFI to the Assistant Project Manager
- Click Edit
- Add Michelle Winters to the Assignee drop down list.
- The Superintendent can also make any other changes necessary at this point, including adding attachments and marking whether or not there will be cost and or schedule impacts.
- Click Save Changes
NEXT STEPS
The RFI will be opened in ProjectSite and responses from these platforms will be transferred to the RFI in Procore.